|
Executive Summary:
This briefing reviews GEF policies
and procedures relevant to protected areas and indigenous peoples. The main
findings of the review are the following:
GEF policies and procedures
continue to support an exclusionary model of protected areas, which entails
the removal of resident populations and indigenous peoples to buffer zones
and their provision with ‘alternative livelihoods’. As such the approach is
out of date and at odds with the requirements of the Convention on Biological
Diversity, the instructions of the Conference of Parties and international
best practice on protected areas.
In GEF projects:
o Participation
of affected communities is often absent or perfunctory
o The
GEF’s own policies and procedures are often not properly implemented
o Traditional
knowledge is often ignored or disregarded
o Land
tenure is not addressed
o Resettlement
is built into project design
o Implementing
agencies often fail to adhere to their own procedures
o Baseline
studies are lacking
o Impacts
are weakly monitored
o Community
resistance to and resentment of GEF protected area projects is widespread.
The briefing recommends that the
GEF urgently:
q
Updates its policies and procedures in
accordance with COP decisions and guidance
q
Adopts a policy regarding Indigenous Peoples, which
secures their rights to their lands and territories, livelihoods and to free
prior and informed consent
q
Revises its Monitoring and Evaluation
Procedures to ensure community participation and use of traditional
knowledge.
|
Introduction:
The
GEF is the international financing mechanism for the Convention on Biological
Diversity (CBD).[1]
The Third Replenishment for the third phase of the FEF (GEF3) amounted to $3
billion for the period July 2002-June 2006. The Conference of the Parties to
the CBD provides guidance to the GEF
Council, which is mandated to convert this guidance into its operational
guidelines in GEF policies and Operational Programmes (for a summary of all
previous CBD guidance to the GEF, see COP 7 document UNEP/CBD/COP7/INF/1).[2]
The GEF Instrument and the GEF Operational Strategy establish that
all GEF-funded activities shall be in full conformity with the guidance
provided by the Conference of the Parties (COP) of the CBD. The Convention also
undertakes periodic reviews of the effectiveness of the financing mechanism.
The CBD has so far undertaken two independent reviews of the GEF in 1998 and
2001. A third review is due in 2004-05. The arrangements, scope, objectives and
methodology for this latest review will be agreed at CBD COP7 in 2004.[3]
GEF support for biodiversity conservation:
A
substantial amount of the GEF’s total funds are allocated to projects under its
biodiversity “focal area”.[4]
Some of this funding has been directed towards ‘enabling activities’ for
national biodiversity studies, conservation trust funds, the formulation of
National Biodiversity Strategies and Action Plans (NBSAPs), national needs
assessments and capacity building for government conservation agencies. Much
GEF funding has also been channelled to the establishment and management of
protected areas – for both individual protected areas and for National Systems
of Protected Areas and for biological corridors. Between 1991 and 2001 the GEF
had spent $960 million on protected areas (average of $96 million per year)
making it one of the key international mechanisms for funding national parks,
biosphere reserves and other conservation areas.
Implications for indigenous peoples:
GEF
policies, projects and programs have major implications for indigenous peoples
because many of their traditional territories have been designated as protected
areas. At the same time, the ancestral lands of indigenous peoples contain
biodiversity and biological corridors of global importance. Indigenous peoples
have protested that protected areas have resulted in the violation of their
rights and have imposed restrictions that undermine their traditional
livelihoods and caused impoverishment.
International best practice
The
recent 5th World Parks Congress (WPC) held in Durban, South Africa,
acknowledged that the costs of protected areas are often borne by indigenous
peoples and local communities. The ‘Durban Accord’ announces a ‘new paradigm’
under which best practice protected area laws, policies, governance and
management must ensure the participation of indigenous peoples in
decision-making on a fair and equitable basis and with full respect for their
human rights.[5]
In relation to indigenous peoples’ rights, the WPC ‘Message to the CBD’ states
clearly:
The Congress also noted that protected areas
may have a negative impact on indigenous peoples, including mobile indigenous
peoples, and local communities, when their rights and interests are not
accounted for and addressed and where they do not fully participate in and
agree to decisions that affect them. It further noted the importance of
securing indigenous peoples' rights to their lands and territories as an
imperative to guarantee sustainable protected areas.[6]
Objectives of the briefing:
The
purpose of this paper is to highlight that GEF policies, priorities and
activities in relation to biodiversity conservation, indigenous peoples and
protected areas are out of date and contain gaps and contradictions, which are
arguably at odds with some CBD provisions and the ecosystem approach. It is
recommended that CBD COP 7 issue new guidance to the GEF to help ensure that
its policies become more consistent with the CBD, its work programmes and with
best practice on protected areas and indigenous peoples.
A. Problems
with existing GEF Operational Programmes
Operational
Programmes (OPs) are supposed to incorporate the guidance of the CBD and are
intended to provide a basic framework for the preparation and design of GEF
projects for specific themes in each GEF “focal area”. In relation to biodiversity,
the GEF has six OPs:
Ø
Arid ecosystems (OP1)
Ø
Coastal, marine and freshwater ecosystems (OP2)
Ø
Forest ecosystems (OP3)
Ø
Mountain ecosystems (OP4)
Ø
Integrated ecosystem management (OP12)
Ø
Conservation and sustainable use of biodiversity
of importance to agriculture (OP13).
Not
withstanding useful standards on participation and traditional knowledge, most
GEF Operational Programmes and projects in support of biodiversity conservation
and sustainable use of natural resources still routinely deal with social
issues by applying the troublesome alternative livelihood approach (Box I). This approach aims to
reduce (perceived) human ‘pressure’ on biodiversity by providing ‘alternative’
money-based livelihoods for indigenous peoples and local people. It also
sometimes involves the relocation of people to rehabilitation sites outside
parks.[7]
Indigenous
peoples and communities who have been affected by these projects complain that
alternative livelihood options do not properly compensate them for their loss
of customary resource rights and subsistence benefits.[8]
They argue that the “alternative livelihood” approach violates their inherent
rights to own, occupy and use their traditional lands, territories and
resources and is anyway often based on flawed assumptions that are not backed
up by scientific data, usually because detailed baseline studies of local
resource use have not been carried out prior to designing a project (see B.
below). Despite these criticisms, support for alternative non-land and
non-natural resource livelihoods remains a dominant theme in the design and
implementation of GEF protected area projects.
Some
GEF Operational Programmes (OP2 and OP3) also dictate that funds for “modified
activities” for “conservation and development projects” and “tenure reform and
land titling” are restricted to buffer zones outside protected areas – indicating that the GEF does not support
indigenous land rights and community development within protected areas – at
least not in forests and coastal and aquatic environments (Box I).
Undermining the provisions and spirit of the
CBD?
By
denying indigenous peoples their rights inside protected areas and by financing
and carrying out projects to persuade indigenous peoples and local communities
to give up traditional land-based livelihoods in return for income-based
livelihoods, it could be argued that the GEF policies and activities risk
undermining the principles of the ecosystem approach and Article 10c of the
CBD, the latter of which requires government parties, as appropriate, to “protect and encourage customary use of
biological resources in accordance with traditional cultural practices...”The
first principle of the ecosystem approach, adopted by the COP in Decision V/6,
states the following:
Principle 1: The
objectives of management of land, water and living resources are a matter of
societal choice
Rationale:
Different sectors of society view ecosystems in terms of their own economic,
cultural and societal needs. Indigenous peoples and other local communities
living on the land are important stakeholders and their rights and interests
should be recognized. Both cultural and biological diversity are central
components of the ecosystem approach, and management should take this into
account. …
Out of date Operational Programmes:
With
the exception of the more recently adopted OP12 on Integrated ecosystem
management, GEF’s biodiversity OPs have not been updated to incorporate the CBD
guidance since COP IV. The current OPs also fail to include the progressive
elements in recently adopted or expanded work programmes, such as the expanded
work programme on Forest Biological Diversity. Among numerous other activities,
this latter CBD work programme recommends, for example, that States-parties
undertake activities to:
(i)
Strengthen the capacity of indigenous and local
communities to resolve land rights and land use disputes in order to
sustainably manage forest biodiversity [Programme Element 1: Goal 4, Objective
3, activity b]
(ii)
Provide incentives for the maintenance of cultural
diversity as an instrument to enhance forest biological diversity [Programme
Element 1: Goal 4, Objective 3, activity d]
(iii)
Create an environment that fosters respect, and
stimulates, preserves and maintains traditional knowledge related to forest
biological diversity [Programme Element 1: Goal 4, Objective 3, activity d].
B. Poor
implementation of GEF and Implementing Agency policies
The
GEF has a policy on public participation (Box II) and has useful standards in
its GEF Operational Programmes on participation and traditional knowledge. It
also has a policy on Monitoring and Evaluation.[9]
These policies rightly require that GEF funded-activities ensure local
participation, address the need and interests of affected communities and
compile pre-project baseline information. The OPs also establish that the GEF
should support specific activities, including support for:
...capacity-building efforts that promote the preservation and maintenance
of indigenous and local communities’ knowledge, innovation, and practices
relevant to conservation of biological diversity, with their prior informed consent and participation [OP2 2.1.9.b,
OP 3.17.j. etc]
However,
despite the GEF’s new focus on “impacts and results” there is much evidence to
show that these important social and cultural elements in GEF policies are
still not being effectively implemented. Indigenous peoples complain that they
are often not even advised of GEF projects until they have already been
approved and implementation has begun – one example is the Philippines: Conservation of Priority Protected Areas Project (CPPAP),
which did not involve local
indigenous communities until the project had already begun.[10]
The GEF’s own review of its biodiversity portfolio in 2001 found that only 20%
of protected area projects had ensured local people felt properly involved. In
a sample of 78 projects, the review found that the extent of participation in
almost half of the projects was either partial
(20%), poor (9%), absent (12%) or unknown (4%).[11]
Likewise,
GEF protected area projects struggle to properly value and respect traditional
knowledge. The same 2001 GEF internal review found:
...little
evidence of such (traditional) knowledge being used in project execution or
in-situ conservation or sustainable use programs...Even for projects working
with indigenous populations, the reviews noted the lack of documentation of
traditional knowledge and practices
The
serious disregard for local and indigenous knowledge and the associated
resource rights of rural communities in GEF projects has caused local people to
come together to resist these interventions. One such case is the GEF-assisted Sundarbans Biodiversity Conservation Project
in Bangladesh where local people complain that traditional cultural wisdom
regarding wetlands management has been almost totally disregarded by the
project. Local opposition eventually caused the Executing Agency (the Asian
Development Bank) to suspend the project half way through implementation until
a thorough review of social, cultural and livelihood issues has been
undertaken.[12]
|
BOX I: A
summary of GEF Operational Programme Number 3: forest ecosystems
[emphasis added] http://www.gefweb.org/Operational_Policies/Operational_Programs/OP_3_English.pdf
Application of CBD Ecosystem Approach: The second CoP reaffirmed that “the ecosystem
approach should be the primary framework of action to be taken under the
Convention”... The ecosystems approach is followed in Operational
Programs...[3.4]
Objectives: Conservation or in-situ
protection of old growth forests and mature secondary forests by establishing and strengthening systems of
protected areas [3.9.a.]; Sustainable use forest management through combining production, socio-economic
and biodiversity goals a range of land uses including combinations of strict protection of reserves,
multiple use and full scale use [3.9.].
Scope: Priority forest areas including areas of: High endemism; High
ecosystem, species and genome diversity; High distinctiveness; Importance to migratory
species; Importance as spawning and nursery grounds; Habitat or species under
threat; High social, economic,
cultural or scientific value; Composition shaped only by a limited extent
by human activities [3.10.a.]
Expected outputs: Protected Areas are established with effective management plans
[3.1.5.a]; Threat Removal e.g.,
through reduced “encroachment” [3.1.5.b.]; Sectoral Integration, including integrated community development
addressing livelihood issues of local and indigenous communities living in buffer zone areas [3.1.5.c]; Sustainable
Use. Sustainable logging and other forest industries [3.1.5.d.]. Institutional strengthening. Stronger
institutions and well trained staff [3.1.5.e]
Monitoring outcomes: Surveys of forest cover, structure and
composition; Population of invasive species; Abundance of keystone species;
Ecological surveys in protected forest areas; Integrity of forest ecosystem
[3.1.2] [NO social, cultural and livelihood indicators are included]
Means of implementation of OP 3: The GEF can support investment, technical
assistance, capacity-building, public education, policy work and targeted
research.
GEF Conservation Activities: Typical activities are: demarcating, gazetting, strengthening and consolidating forest
protected areas; remedial actions in forests under threat...identifying
processes and activities that have or are likely to have adverse impacts on
biodiversity; controlling alien species and capacity building for biosafety;
piloting activities and tools, such as rapid ecological/social assessment; data analysis; conservation of biodiversity
important to agriculture; “supporting capacity-building
efforts that promote the preservation and maintenance of indigenous and local communities’ knowledge, innovation, and practices
relevant to conservation of biological diversity, with their prior informed consent and participation ...”
[3.17.j.]
GEF Sustainable Use Activities “Typical GEF sustainable development activities
would be in areas surrounding critical
habitats”. In addition ...“consistent with the incremental cost approach”...
the GEF can finance: ...integrated pilot projects for alternative livelihood projects to local and indigenous
communities residing in buffer zones;
integrated conservation and
development projects around
protected forests; participatory
management of natural resources, and alternative livelihoods; tenure
reform and land titling in buffer
zones; sustainable production and use of natural products; community
woodlots to reduce pressure on protected forests; sustainable logging
regimes...; (and) capacity building
for indigenous and local communities for maintenance of traditional and local
knowledge [3.1.8]
Addressing
project risks: Projects will address
risks to desired outputs by (a) Using and adapting best practice and baseline
indicators to monitor impacts (b) “Ensuring that local communities accept
and respect the boundaries of protected forests”... (by) scaling up and
expanding successful community development, participation; and incorporating
the knowledge of local and indigenous
communities [3.1.9.b.]
Public involvement: There should be: “emphasis on local participation
and local stakeholders” [3.22a.]. “Strategic partnerships will be sought,
where possible, among relevant stakeholders (e.g., government, NGOs,
academia, the private sector, local communities, and indigenous groups)...on
the basis of comparative advantage...Partnerships will be appropriate to
local conditions and build on local expertise [3.2.3]
Resources: “GEF resources will be used to meet the incremental
costs of activities in this Operational Programme”.... [3.2.4]
|
More
disturbing is the fact that where GEF projects do deal with traditional knowledge,
they seem not to include any measures to respect the right of free prior and
informed consent in relation to access to and use of such knowledge – even
though this standard has been explicitly required for GEF projects by the COP
and is contained in existing GEF OPs.
There
is also continuing evidence that the World Bank as one of the GEF’s main
Implementing Agencies, still struggles to mainstream environmental and social
concerns in its projects. For example, a recent review of the implementation of
the Bank’s Indigenous Peoples Policy found that more than half projects
adversely affecting indigenous peoples were found to have “...inadequate measures to mitigate the adverse
impact of the project activities”, while the policy was not applied at all
in 38% of the projects that affected indigenous peoples, demonstrating a major
failure in the application of the policy.[13]
Lack of adequate baseline studies:
One
of the most serious and persistent problems in implementation is the failure of
Implementing Agencies to carry out proper social, cultural and biological
baseline studies prior to project approval and implementation. The failure to
undertake such studies violates both the GEF’s own Monitoring and Evaluation
Policy and the IAs own internal policies. The failure to carry out these
baseline assessments means that indigenous knowledge systems, land tenure
regimes and their customary resource use practices are disregarded or poorly
understood in GEF projects.[14]
Failure to deal with land tenure:
Despite
requirements to address land tenure issues under the Bank’s own internal
standards, GEF projects often fail to adequately deal with critical land rights
and resource rights issues, though these issues may sometimes be mentioned in
project documentation. In the CPPAP project mentioned above, indigenous peoples
have criticised the project as it does not seek to resolve Aeta claims to their
ancestral territories.[15] Even where projects seek to target indigenous
peoples, it is evident that these crucial issues are being left out of project
design – in direct violation of IA policies.
For
example, in the GEF-assisted Indigenous
Management of Protected Areas in the Amazon (PIMA) project in Peru,
indigenous communities have complained that the project design fails to address
their land claims to traditional territories which have protected areas
superimposed on top of them. In the same way, the more recent Participatory Management of Protected Areas
Project, also in Peru, likewise
excludes land tenure issues from project design yet is financing a project
where widespread land tenure conflicts are known to exist and are reported in
project documents.[16]
The 2001 GEF review of its biodiversity programme confirms that this failure to
address land tenure gap is a feature of many GEF biodiversity projects:
Part of the problem with project achievements might be due to somewhat
less attention being paid in project design and implementation to livelihood
and tenure issues and to underlying causes...Issues relating to tenure,
property rights, and access must...be addressed as part of each initiative[17]
The
failure to deal with tenure issues means that GEF projects risk undermining the
land base of traditional knowledge systems, as recently highlighted in by the
CBD Ad Hoc Working Group on Article 8 j which affirms:
Parties should be encouraged, in accordance with national domestic law
and international obligations, to recognize land tenure of indigenous and local
communities, as recognized rights and access to land are fundamental to the
retention of traditional knowledge...[18]
Box II: GEF (1996) Guidelines
on Public Involvement in Projects Financed by the GEF
(emphasis added)
Available (English only) at: http://www.gefweb.org/Operational_Policies/public_involvement/public_involvement.html
Status: An operational policy adopted by the GEF Council
in April 1996.
Implementation
responsibility: Recipient country
and Implementing Agencies (World Bank, UNDP or UNEP as appropriate).
Coverage: The principles and requirements will be applied by
the GEF Secretariat, the Implementing Agencies (IAs) and project executing
agencies (government agencies, UN agencies, NGOs etc.) and other relevant
bodies.
Definitions:
Public
involvement consists of 3
processes: information dissemination, consultation and “stakeholder”
participation. (para. 5)
Stakeholder: individuals, groups or institutions that have an
interest in the outcome of a GEF-financed project (para. 5.)
Stakeholder
participation: “...where
stakeholders collaboratively engage...in the identification of project
concepts and objectives, selection of sites, design and implementation of
activities, and monitoring and evaluation of projects.”
Principles
of Public Involvement:
· ... to be socially sustainable, projects should, as appropriate, address
the social, cultural, and economic needs of people affected by GEF-financed
projects [II.10]
· ... relevant social issues will be taken into account in the design,
implementation, and evaluation of projects [II.10]
· Governments should promote public involvement in the
identification of project concepts and throughout the project cycle, with the
help of the Implementing Agencies [II.11]
· The Implementing Agencies will work closely with
governments and project executing agencies to involve stakeholders at the
earliest phase of project identification and throughout design,
implementation, and evaluation [II.11]
· ... “all public involvement activities should be
based on local needs and conditions...biodiversity projects affecting
indigenous communities may require more extensive stakeholder participation
than global projects which focus on technical assistance and capacity
building at the national and regional levels” [II.12]
· ... The Implementing Agencies will include in project budgets,
as needed, the financial and technical assistance necessary for recipient
governments and project executing agencies to ensure effective public
involvement
· The Implementing Agencies will work with governments
and project executing agencies to ensure...(a) accessible information to as
many stakeholders as possible; (b)...broad as well as project-specific
consultations, especially at the local or
sub-national levels; and (c)
...participation of stakeholder groups throughout the project cycle...(including)
awareness raising and capacity strengthening activities [II.13]
· Public involvement activities will be conducted in a
transparent and open manner. All GEF-financed projects should have full
documentation of public involvement activities
· The GEF Secretariat will undertake the following to
facilitate effective public involvement in all GEF-financed
projects...including participation in design, planning, implementation,
monitoring and evaluation [II.15]
· The GEF Secretariat will...Ensure that funding is
available to recipient governments, executing agencies, and, as appropriate,
NGOs for conducting effective public involvement... [II.15]
· The Implementing Agencies will develop guidelines
for public involvement in their own GEF-financed projects, and should
include...Modalities for incorporating public involvement in projects, and
addressing social issues, starting at the earliest stages of the project
cycle, and recognizing the difficulties and long-term nature of cultivating
local participation and Financing options during project preparation,
and within project budgets, to facilitate design and implementation of public
involvement activities...including involvement of local groups...; [II.16]
|
C. Ongoing weaknesses in GEF
Monitoring and Evaluation framework
The
GEF still suffers serious weaknesses in its monitoring and evaluation framework
despite major efforts to overhaul and improve its monitoring capacity in recent
years.[19]
It is startling that after ten years the GEF Secretariat has still so far
failed to comply with the GEF 1996 Policy on Public Involvement, which requests that it develop detailed
guidelines on how to assess the effectiveness of the implementation of the
policy (at paragraph II.15). One of the most serious gaps is the continuing
lack of adequate results-based and performance-based social indicators for GEF
projects. The second independent review of the GEF undertaken for the
Conference of the Parties of the CBD in 2001 confirms that this fundamental
flaw in GEF monitoring remains (see also section 5.):
“The
difficulty arises in monitoring of results and impacts of GEF work. Our
research suggests that project monitoring and evaluation has tended to focus on
inputs and outputs, with less focus on results and impacts”[20]
Given
the serious lack of official data on the impact of GEF projects on indigenous
livelihoods, indigenous representatives participating in the GEF Council called
on the GEF in 2001 to review such impacts. Indigenous participants were very
pleased that the GEF responded in a timely manner in 2002 by launching a review
of “Local Benefits and GEF Focal Areas”. The completion of the first phase of
this review in 2003 confirmed:
The review has found that reporting of benefits is given little systematic
attention...Fundamentally the type of project reporting submitted by the
Implementing Agencies to the GEF is not intended to provide adequate
information on local livelihood benefits and impacts
The Third Study of GEF’s Overall Performance
(OPS3) is to commence in 2004 and will be completed by mid-2005. A new and
in-depth study on GEF activities in relation to biodiversity conservation will
inform the OPS3 assessment. It is significant that a primary goal of this third
review to be undertaken by the GEF Monitoring and Evaluation Unit is to assess
the results of GEF Operational
Programs and outcomes of GEF-assisted activities. At this stage, there is no
mention of the need to review the social impacts of GEF biodiversity projects.[21]
In contrast, the
proposed methodology for the third independent CBD review of the financing
mechanism instructs reviewers to use the GEF local benefit review.
D. Fragmented treatment of
social, equity and poverty issues
The
Local Benefits review has already validated many of the concerns expressed by
indigenous peoples regarding the lack of proper treatment of social, rights and
poverty issues in GEF projects. The initial desk review of 84 projects in GEF
Biodiversity (BD) focal area found that few
“...projects have yet developed explicit
approaches to operationalize poverty – environment
linkages at the field level...” and there is “...little evidence to suggest projects are considering equity concerns”.
The review also found:
...projects do
not seem to systematically consider possible negative social impacts, either at
the design phase or during implementation. Given that many of the projects are
creating and/or strengthening protected areas, partly through components which
enforce restrictions on community access to and use of resources inside those
areas, there is a significant possibility that negative impacts may be
associated with such project activities[22]
Although
COP VI of the CBD highlighted that the GEF should focus on poverty eradication as
one of the “first and overriding priorities of developing countries,[23]
the GEF report to COP VII does not deal with the question of how it has tried
to address the issue of poverty alleviation.[24]
E. Gaps in GEF standards and
accountability
Indigenous
peoples’ organisations and NGOs have pointed out gaps in the GEF policy
framework for several years. They point out that the GEF does not have a policy
on social or poverty risk assessment.[25]
The Implementing Agencies like the World Bank also lack internal policies on
social and cultural impact assessment. Nor does the GEF have a specific policy
on indigenous peoples – something indigenous peoples have been advocating for
at the GEF Council for many years.[26]
It is also significant that indigenous peoples reject some of the policies of
the implementing agencies as inadequate to protect their rights, particularly
the World Bank’s proposed new draft policy (OP/BP4.10) on Indigenous Peoples. [27]
Since
1994, the GEF has reportedly adopted a general rule that it does not fund
involuntary resettlement, although this crucial institutional safeguard has yet
to be consolidated in official GEF policies.[28]
In the meantime, it is clear that GEF projects continue to include the relocation of indigenous peoples to areas
outside protected areas (even if such relocation might be officially
financed by another agency like the World Bank).[29]
At the same time, its 1996 project cycle guidelines still allow for
“resettlement” in GEF projects, though the type of resettlement permitted is
not defined nor qualified in any way.[30]
Accountability gaps:
The
GEF does not have appeals and complaints procedures for communities who
have been adversely affected by GEF projects, though NGOs and indigenous
representatives may raise concerns formally via project managers and ultimately
in the GEF Council. In short, there are no means of appeal by affected people
regarding the violation of GEF policies.
F. Is
the GEF moving with the times?
It
is significant that the more recent “multi-focal” Operational Program (OP12) adopted
in 2000 affirms that the GEF will not support:
- activities that may
result in perverse incentives for integrated ecosystem management or may
have negative environmental or social
impacts;
- establishment of
agricultural systems that displace affected communities to marginal lands.[31]
Unfortunately,
the same OP does not directly address land tenure, land titling and livelihood
issues. However, there are signs that the GEF is beginning to acknowledge the
importance of clarifying property rights and shifting the ownership of land and
natural resources to communities.[32]
There are also indications that the GEF is seeking to promote better community
involvement and (at least) “limited” community use of park resources, and that
some community-based natural resource management and poverty reduction projects
are appearing in its portfolio.[33]
At
the same time, there are indications that some GEF projects can get it right
and genuinely seek to respect indigenous peoples’ rights. Of particular note is
the UNDP-run Small Grants Programme (SGP). Though not without problems, the SGP
has actively sought to address land tenure issues and to respect indigenous
knowledge.[34]
There is an urgent need to expand and scale-up these successful experiences –
as already noted in the Second Overall
GEF Performance Review completed in 2002[35]
and the Third Independent Review of the
Small Grants Programme.[36]
For
its part, UNEP is also promoting interesting projects on “integrated ecosystem
management” (IEM) in line with OP12, which aim to integrate, recover and value
traditional ecological knowledge.[37]
In
general, however, socially aware and rights-based approaches and other best
practices are not institutionalised in GEF policies and procedures and not
mainstreamed in GEF activities.
Recommendations:
The
GEF needs to update its policies and Operational Programs to ensure its
projects respect the rights of indigenous peoples and apply the principles of
the CBD and the ecosystem approach more effectively. To this end, the Seventh
Conference of the Parties of the CBD should issue specific guidance to its
financing mechanism in relation to Protected Areas and in-situ conservation
(Article 8) and Sustainable Use (Article 10). Specifically the GEF should:
q
Update GEF Operational Programmes, policies and
procedures relating to biodiversity to ensure they are fully consistent and
up-to-date with:
(i)
All recent guidance from the CBD COP to the Financial
Mechanism, including guidance from COP VII;
(ii)
Current CBD work programmes, including those relating
to Article 8j and related articles, forest biological diversity, mountain
ecosystems, coastal, marine and freshwater ecosystems as well as the work
programme on protected areas;
(iii)
International best practice on indigenous and local
communities and protected areas, including measures to ensure that all
decisions on existing and new protected areas are made with the free prior and
informed consent of concerned indigenous peoples in the area;
q
Take practical steps to better implement previous
COP guidance in relation to Article 8j and related articles;
q
Support the implementation of Article 10c of the
CBD to promote and protect customary use and management of biological diversity
by indigenous peoples and local communities, including their tenure rights over
lands and resources and respect for customary laws pertaining thereto;
q
Facilitate the establishment of indigenous and
community conservation areas;
q
Replace the concept of “alternative livelihoods”
with a sustainable livelihood approach, which
respects customary resource rights and builds on traditional land-based
livelihoods and resource use practices;
q
Adopt a specific policy on Indigenous Peoples
with provisions and standards that are acceptable to the rights
holders/intended beneficiaries of the policy;
q
Formulate as a matter or priority transparent
procedures to implement the principle of free and prior informed consent in GEF
projects that involve traditional knowledge elements or affect the lands or
resources traditionally use or occupied by indigenous peoples;
q
Formalise the prohibition of involuntary
resettlement in GEF projects;
q
Update its Operational Programs on biodiversity
to properly address land and resource rights, livelihood security and poverty
alleviation issues;
q
Adopt a policy on social and cultural impact
assessment based on best practice, such as the Akwé:kon guidelines;
q
Develop a specific formal and binding public
policy on accountability and appeals standards GEF operations;
q
Implement measures providing for the restitution
of lands, territories and resources taken without the prior and informed
consent of indigenous peoples as a result of and present GEF-assisted projects;
q
Reform incentive structures in the GEF and
Implementing Agencies to ensure better integration of social and rights issues
in GEF projects and more effective implementation of GEF revised policies;
q
Enable indigenous peoples and civil society
organisations to comment on draft TORs for 3rd Overall GEF review (OPS3);
q
Ensure OPS3 assesses the social and poverty
impacts of GEF biodiversity projects and draws on the findings of the GEF Local
Benefits Study;
q
Include participatory assessments with affected
communities in OPS3 and invite independent community monitoring and evaluation
reports as part of both GEF and CBD reviews;
q
Incorporate successful rights-based approaches
to social issues and land tenure such as those used in the Small Grants
Programme in Medium-sized and Full Size GEF Projects
________________________________________________________________________
[1] The GEF is also the financing
mechanism for the United Nations Framework Convention on Climate Change
(UNFCCC), The United Nations Convention to Combat Desertification (UNCCD) and the Stockholm Convention
on Persistent Organic Pollutants. It also provides support to Cartagena
Protocol on Biosafety, the Montreal Protocol of the Vienna Convention on Ozone
Layer Depleting Substances, and various agreements on the protection of
international waters.
[2] CBD (2003) Financial
Resources and Mechanism (Articles 20 and 21) – compilation of previous guidance
given to the financial mechanism by the Conference of the Parties UNEP/CBD/COP/7/INF/1, 9 December 2003
[3] CBD (2003) Financial Resources
and Mechanism (Articles 20 and 21) – Arrangements for the third review of the
effectiveness of the financial mechanism
UNEP/CBD/COP/7/17/Add.5
[4] The other five GEF focal areas include: climate change,
international waters, ozone layer depletion, land degradation and persistent
organic pollutants (POPs).
[7] E.g., Argentina Biodiversity
Conservation Project (Argentina: 1999-present); Bwindi Impenetrable National Park and Mgahinga Gorilla National Park
(Uganda: 1995-2000).
[9] GEF (2002) Monitoring
and Evaluation Policies and Procedures GEF: Washington DC